Monday, November 29, 2010

Guidance on the new "Permit Extension Act"

Back in August, I alerted clients and colleagues to the new “Permit Extension Act”, which provides a very valuable two-year extension to qualifying real estate development permits that were in effect or existence between August 15, 2008 and August 15, 2010.  Three weeks ago, the Executive Office of Housing and Economic Development (EOHED) issued helpful guidance in the form of “Frequently Asked Questions” to assist local Conservation Commissions, the Department of Environmental Protection (DEP),  property owners, wetlands scientists and engineering consultants in implementing the Act.

The FAQ clarifies and confirms many aspects of the Act, such as:

 The Act automatically extends the permit by operation of law, so that a permit holder and issuing agency are not required to take action to activate the extension. However, an issuing agency may issue an extension form to a permit holder who requests such a document.

 The Act is not limited to state-issued permits; the two-year extension applies to all qualifying permits issued by any town, city, regional or state entity.

 Permits related to pre-development activities, such as the clean-up of oil or hazardous materials, are not affected by the Act. Such pre-development activities are considered to be independent undertakings outside the context of a larger development project and, therefore, are not covered by the Act.

 The Act extends building permits that were issued or in effect between August 15, 2008 and August 15, 2010.

 MEPA certificates, decisions, and waivers are covered, so that qualifying certificates will have two additional years before a “lapse of time” will have occurred that would otherwise have triggered a Notice of Project Change or a new Environmental Notification Form.

 Importantly, the Act revives and extends any permit or approval that may have expired during the qualifying period of August 15, 2008 through August 15, 2010. Thus, for instance, “a permit that expired on July 1, 2009, is now revived and set to expire on July 1, 2011.” Also, a permit is revived even if an extension had been previously denied by the agency.

 The Act provides an additional two years to the original term of the permit even if it was not due to expire until after the qualifying period of August 15, 2008 through August 15, 2010. Thus, “if a permit or approval was due to expire on September 1, 2011, it will now automatically expire on September 1, 2013.”

 However, a permit that had been revoked during the qualifying period is not extended, because the Act specifically preserves the issuing agency’s authority to suspend or revoke a permit. However, the agency must have an independent reason authorized by the terms of the permit in order to revoke or suspend the permit. The agency cannot attempt to avoid the two year extension by revoking or suspending the permit.

 The Act does not protect a permit holder from enforcement actions to address noncompliance. The issuing agency’s enforcement authority is retained.

 The Act does not extend mitigation that was required as a condition of the original permit. All conditions that applied to the permit continue to apply, so that the permit is subject to the same substantive terms as when it was originally issued. However, any interim deadlines established by the permit are extended for two years, according to the FAQ.

 The FAQ indicates that a permit that was pending “adjudicatory appeal” during the qualifying period is not extended. In contrast, a permit pending “judicial appeal” would qualify for an extension if the court were to ultimately uphold the permit.

Of course, the complete text of the FAQ and the Act should be reviewed to evaluate the specific workings of the statute.
Please contact me if you or a colleague has a question on the Permit Extension Act or any real estate development permits affected by the Act.